North Cedar Streetscape Project

Streetscape Construction in Progress

 2021 North Cedar Streetscape Project and other various Downtown Improvements are underway!

As work continues, you can watch the progress as it takes place via the Downtown Owatonna Live Camera Stream any time by clicking here for the YouTube site or by visiting our 2021 North Cedar Ave Streetscape Project page

9/24/2021 - ISG Update: 

Work This Past Week

  • The remaining services and major utilities were completed within the 300 block 
  • Removals occurred through the remainder of the 200 block
  • The temporary water line has been setup in preparation for connecting temporary water services within the 200 block
  • Bituminous paving occurred in the alley next to 107 West Rose Street to reestablish the parking stalls and allow for the alley to be reopened to Rose Street
  • Foundations are being set for the seat blocks and planter beds


Upcoming Work

  • Foundations for the seat blocks and planter beds will continue to be placed
  • A subdrain will be installed along the curb line
  • The road subgrade will be prepped, and the subbase and base will be hauled in and placed in preparation for concrete paving

Concrete paving on the 300 block is anticipated to begin in approximately two weeks



Please feel welcome to contact Reese Sudtelgte or Anthony Lance of ISG with any questions regarding the project or any other items of concern.

For updates from ISG regarding this project, visit ISG's Project Website, scroll to "Stay Connected" and fill out the form titled "Sign up here for project updates"

Facebook Twitter Email